From Martin Carvey | Project Manager
Throughout the opening months of 2022, the KentVision project team has continued to work through prioritisation and management of ongoing helpdesk tickets to clear the path for the major changes that we know are still required for the system to be fully operational. A lot of this work takes place ‘behind the scenes’, ensuring we have the right approach to collaboration across areas and adjusting to a more iterative delivery model with appropriate testing time.
This means that benefits aren’t realised as quickly as many across both the project and wider University would like – my thanks again to all system users and our key stakeholders in particular for their continued engagement with this as I know the impact of the system’s current state remains a real challenge across a number of areas. However, the work in recent weeks is critical to us being able to start delivering regular improvements in a managed way without furthering risk to our regular work.
Roadmap for deliverables
Consultations continue across the University, with an updated roadmap tracking seven deliverables that are currently scheduled, with the balance being assessed against what can be realistically delivered. Priority areas at high level factor in Change of Circumstances, Board of Examiners and Data Quality/Statutory Data, with user stories are being created in each area to ensure we have thought through what the impact of each change will be, and ensure that the appropriate solution can be delivered in each case. A delivery plan for the new training environment has also been established, with both shared with key stakeholders shortly.
Continued engagement
Benefitting from the insight and experience of those in key teams across the University remains central to delivering a product that works as it needs to. In recent weeks we have allocated additional resource to make sure more real time data and reports can be provided, with clarity on progress and risks on key deliverables throughout.
Next steps
With these project improvements in place, our aim remains that people begin feeling the benefit of improvements across the system from this Spring onwards. Using an Agile delivery model, our initial priorities have been agreed with KV Project Board, and KV Operational Group members, ensuring that we have fully tested and delivered changes required ahead of the upcoming exam term and other committed timelines.
This remains a challenging project and I am especially grateful to all of those who are feeding in their on-the-ground experience of how the system currently works, including what they need it to do in future – this is invaluable to the project, and I know it is not easy when people are also impacted by the issues with its current form. By my next update, I am confident that the detailed work in recent weeks will begin to bear real fruit, with improvements across areas that make a real difference to how we work across these initial priority focus areas.